The State Railway of Thailand (SRT) is pressing to resolve its concession dispute with Asia Era One by November 28, 2026, as the private partner maintains its request to terminate the contract for the long-delayed high-speed railway linking Don Mueang, Suvarnabhumi and U-Tapao airports.
Anan Phonimdaeng, the SRT governor, said on Thursday (November 19) that the agency would consult the Office of the Attorney General on further legal steps if the talks failed to produce an agreement.
The SRT is also preparing for its subsidiary to take over Airport Rail Link operations on February 1, 2027, with Anan pledging that passenger services would continue without interruption.
The SRT has issued a Notice to Proceed (NTP) and followed up with Asia Era One, Charoen Pokphand (CP) Group-led consortium, to require work to begin under the existing concession, Anan said.
Asia Era One has rejected the NTP and reiterated that it had already notified the SRT of its intention to terminate the agreement, according to Anan.
“The contract provides 60 days for negotiations to resolve a dispute. That period ends on November 28,” Anan said.
“If we cannot reach an agreement, we will have to proceed through the legal system. The SRT will consult the Office of the Attorney General on how to proceed,” Anan added.
Anan said the SRT’s priority was to get its partner to proceed under the original agreement and prevent further delays.
Separately, the SRT said it had filed a claim at the Central Administrative Court on October 21 against Asia Era One and related guarantors, seeking a total of about 13.34 billion baht in Airport Rail Link rights fees and default interest.
The SRT has instructed S.R.T. Electrified Train Company Limited (SRTET) to prepare to take over management and operation of the existing Airport Rail Link on February 1, 2027.
Anan said preparatory meetings and progress reviews had already been held, and assured passengers that services would continue during the transition.
An interim agreement signed by the SRT and Asia Era One on September 29 covers continued operation from October 1, 2026, to January 31, 2027.
The February handover concerns the existing Airport Rail Link service, not the start of operations on the proposed high-speed railway.
The SRT signed the original 50-year public-private partnership (PPP) agreement with the CP-led consortium on October 24, 2019. The 220-kilometre project was valued at about 224.5 billion baht when the agreement was signed.
In 2024, the Eastern Economic Corridor (EEC) Policy Committee endorsed proposed changes to payment terms, including state contributions tied to construction progress rather than the start of train services, and instalment payments for the Airport Rail Link rights fee. The proposals required further negotiation and approvals.
In July, Asia Era One cited restrictions affecting the Makkasan project site, unresolved contract amendments and changes in economic and financing conditions among the obstacles to proceeding with the project.
Chula Sukmanop, secretary-general of the Eastern Economic Corridor Office (EECO), said on October 26 that feasibility assessments had raised serious concerns about the project’s commercial viability and banks had declined to provide financing.
Chula said proposed contract amendments had been judged legally permissible but would not solve the financing problem. He maintained that the concession remained binding pending formal termination.
Chula outlined possible alternatives if the existing contract ends, including direct public investment or a new PPP. A redesigned scheme could reduce operating speeds from 250 kilometres per hour to 160 km/h to lower costs.
Chula’s alternatives were presented as options for assessment, not as an approved replacement project.