The Mass Rapid Transit Authority of Thailand (MRTA) has reported progress on the Orange Line, which remains under construction, with figures current as of August 2026.
MRT Orange Line: Thailand Cultural Centre–Min Buri (Suwinthawong) section
MRT Orange Line: Bang Khun Non–Thailand Cultural Centre section
Meanwhile, Bangkok Expressway and Metro Public Company Limited (BEM) released a timeline for preparations to operate the Orange Line.
On the eastern section, between Thailand Cultural Centre Station and Yaek Rom Klao Station, the first train has completed production and factory testing in Turkey and is being sent to Germany for trial runs to confirm its quality and safety.
It will then be shipped to Thailand.
The second train is undergoing testing in Turkey.
The first train to complete the testing process is expected to arrive in Thailand in late November.
Further trains are being produced as scheduled.
BEM estimates that trial service on the eastern section could begin in late 2027, with full service beginning as planned in early 2028.
Once the eastern section opens, it is expected to handle up to 100,000 passenger trips per day, with the figure projected to rise to 300,000 passenger trips per day.
Meanwhile, civil works on the western Bang Khun Non–Thailand Cultural Centre section are 39% complete.
The target is to complete the work in time for services to begin in 2030.