Don Mueang passes AOT readiness test, nearly set for October 1 opening

FRIDAY, SEPTEMBER 21, 2012
Don Mueang passes AOT readiness test, nearly set for October 1 opening

Don Mueang Airport is 95 per cent ready to serve low-cost airlines and passengers when it is fully relaunched on October 1, Airports of Thailand (AOT) said Friday.

 

Paranee Vatanotai, director of the airport, said it had arranged with relevant parties to prepare transport service between Don Mueang and Suvarnabhumi Airport.
AOT conducted a readiness check of Don Mueang Friday. The test used 135 people to act as passengers with luggage preparing to board an AirAsia flight from Bangkok to Singapore departing at 1.10pm. According to AOT, the test ran smoothly.
The Nation