According to PTT, tasked to be in charge of natural gas procurement for electricity generating, the supply resumed late April 12, 30 hours before schedule.
EGAT Governor Sutas Patamasiriwat announced today that during the April 5-12 period, there was no power blackout or brownout. Since April 12, combined cycle power plants have been switched from diesel and bunker oil to natural gas. During the 8-day period, 86.22 million litres of bunker oil and 38.80 million litres of diesel were consumed in lieu of natural gas, 5.8 million and 11.2 million litres below expectation, respectively.