Indonesia will see a massive increase in power supply this year thanks to 19 coal-fired power plants, with a combined operational capacity of 3,620 megawatts.
This year’s power supply, if materialised, will be the biggest since the 1998 financial crisis, according to the country’s Energy and Mineral Resources Ministry.
The plants are part of the delayed first phase of the 10,000MW programme, launched in 2006, to fast track the construction of power plants.
The ministry’s director-general for electricity Jarman Sudimo said yesterday that some of the plants were due to be completed last year.
“However, due to some technical problems, the trial period to test their operations had to be extended, causing a delay in the commencement of their operations,” Jarman said.
Some of the problems faced during the trial included failure to meet expected production capacity as well as unplanned shutdowns, according to Jarman.
Despite the issues, Jarman said the government remained upbeat that most of the projects, particularly plants such as the 3x350MW Pelabuhan Ratu plant in West Java and the 2x315MW Pacitan plant in East Java would be completed in the first quarter of this year.
In the first half of the year the government expected the combined capacity of the online power plants to be around 1,400MW, he said.
“There are many plants with low capacities. So I do not foresee their completion facing any trouble,” he said.
State power company PT Perusahaan Listrik Negara (PLN) has warned the government to not rush into operating the plants as the company would first examine their reliability.
PLN president and director Nur Pamudji said the company was focusing on the sustainability of the plants before approving their operation.
He said it would be useless if a plant had a big capacity, but failed to supply the power efficiently and uninterrupted.
Indonesia, whose economy accounts for 40 per cent of Southeast Asia’s output, struggles with protracted infrastructure capacity problems, including power plants.
The capacity shortfall, according to economists, has hindered the country’s economy from growing over 6 per cent.
PLN’s director of planning and risk management Murtaqi Syamsuddin said Indonesia’s annual electricity consumption would rise by 9.9 per cent in line with the annual economic growth of 6 per cent.
“This means the country needs additional power of 4,500MW per year,” he said.
“It also needs additional funds of 80 trillion rupiah [Bt252 billion] to support this. PLN’s financial coverage will only be around 40 to 45 trillion rupiah,” he said.
In 2013, PLN would invest around 64.9 trillion rupiah, up from 50 trillion rupiah in 2011. Out of the total investment, around 20.8 trillion rupiah will be from loans and 18.2 trillion rupiah from the firm’s internal funds.
In addition to the 3,620MW projects initiated by PLN this year, the government also expects another 1,000MW of additional supply from private companies under the independent power producer scheme, such as the Poso plant in Central Sulawesi.
This year, the government estimates a 9-per-cent increase in the power plant installed capacity to 47,966MW compared with last year. However, the supply will remain insufficient to support expansion in the manufacturing sector.
According to PLN, the peak consumption in Java-Bali alone has added to another 20,500MW, while Sumatra comes second with 5,000MW.
The eastern part of Indonesia including Kalimantan has a peak production of around 3,000MW.
Hanan Nugroho, a senior planner with the National Development Planning Agency, currently a research fellow at Harvard University for energy development, said that the country’s target to increase power supply by 3,500 to 4,500MW per year is still small when compared to other countries such as China or Malaysia.
“The real problem of developing more plants in Indonesia is quality control,” he said.
Furthermore, the government must map out the whole plan for the construction of power plants, from the locations to land acquisitions, to avoid any bureaucracy issues that would postpone the projects, Hanan said.
All projects under the first 10,000 programme are initially scheduled for completion in 2011. However, due to delays the government aims to complete construction by 2014.
The National Energy Council has warned that the long-term economic development plan needs to be supported with additional energy supplies to meet demand, which is expected to increase threefold by 2030.